Project Update – Gulf Star Marina (12-11-18)
Welcome To Our Barn Raising... Boat Barn That Is! The first panel at Gulf Star Marina has been lifted! Check out this quick video of the process from our [...]
Project Update: Gulf Star Marina (12-10-18)
Here's a look at Gulf Star Marina from our new drone! We're picking up panels on 12/11.
Project Update: Gulf Star Marina (12/4/18)
Here's a quick video of our pour at Gulf Star Marina this morning! We are pouring panels this morning, and we're preparing to pull them up next [...]
Gulf Star Marina Shuttle Testing Project Update
As of today, most of the ASAR crane pieces have shipped from our manufacturing facility in Austria, to Gulf Star Marina in Fort Myers, FL. While the masts and platforms [...]
Project Update: Gulf Star Marina (11/10/18)
Here's a quick look at Gulf Star Marina! We will be pouring the slab for the crane path on Tuesday, the 13th.
Project Update: Gulf Star Marina (11/6/18)
Excavation for the main crane path is underway at Gulf Star Marina!
Project Update: Greenscapes (11/2/18)
Paint is going on at Greenscapes! The parking lot approach is completed, including the multi-football field sized lot in the back.
Project Update: Summit Church (10/26/18)
At Summit Church, we are now on the second level of CIP beams with only a few feet left to reach the top of the parapet. Structural steel will be [...]
Project Update: Greenscapes (10/25/18)
At Greenscapes, work is progressing in the parking lot areas with backfill, base rock and site concrete being installed. Our painter has applied primer to the building and it [...]