Project Walkthrough: Physicians Regional Building (11/2/2020)

Now that the walls are up at Physicians Regional Building, we're working on panel connections, stair tower floors and exterior patch & rub. Our steel subcontractor is currently working on the main steel structural components, and we'll be able to do slab-on-deck pours for the upper floors in about 3-4 weeks. Since we're finished [...]