Project Update: Gulf Star Marina (11/20/19)
Work continues at Gulf Star Marina, with the boat shuttle beams being poured soon, windows are being put into place by Florida Glass & Aluminum, and more work is [...]
Work continues at Gulf Star Marina, with the boat shuttle beams being poured soon, windows are being put into place by Florida Glass & Aluminum, and more work is [...]
At Gulf Star Marina, our ASAR - A Smart Storage Solution Crane's construction is well underway! The main structure has been lifted in and assembled, so we were finally able to close [...]
Yesterday, our partners at LTW began piecing together the beginnings of the ASAR stacker crane being installed at Gulf Star Marina. Over the next couple of weeks, we'll be watching [...]
Out with the old and in with the new is what they say, and the out with the old part is well underway at Gulf Star Marina. As we [...]
Greeting the sun again at Gulf Star Marina! Here’s a quick video of our progress this morning. As you can see, demolition continues in the parking lot, the bunk [...]
Work has begun on the parking lot replacement at Gulf Star Marina! In an attempt to not inconvenience the restaurant, we will be proceeding in 3 sections, turning over [...]
Happy Friday! We’re continuing to work diligently at Gulf Star Marina, with our focus being on finishing the seawall and pouring the bay toppings. We are also working on [...]
The fun never ends at Gulf Star Marina! We're currently working on pouring bay toppings, as well as finishing the seawall with the help of our friends at Kelly [...]
Out with the old and in with the new! The new seawall at Gulf Star Marina is rapidly taking shape. Unforeseen subsurface conditions have caused some headaches, but it's [...]
Kelly Brothers Inc. is on site to begin the dock removal and seawall work. As you can see, they are moving in by sea, and performing this portion from [...]